News

Demolition of Wing 5 Outer Shell

All of the interior demolition work is done. Actual demolition of the outside shell has begun, and is anticipated to be complete by late May 2013.


Demolition of Wing 4 Outer Shell- completed 19 April 2013

All associated work on the removal of Wing 4 is complete.


Demolition of Wing 3 Outer Shell - Completed 13 March 2013

All associated work on the removal of Wing 3 is complete.


Demolition of Wing 3 Outer Shell

All of the interior demolition work is complete. Demolition of the outside shell has begun, and is anticipated to be complete by late March 2013.


Demolition of Wing 2 Outer Shell - Completed 8 Feb 2013

All associated work on the removal of Wing 2 was completed ahead of schedule.


Washington Post Coverage of the Navy Annex Demolition

The demolition work on the Navy Annex was recently featured in the January 6, 2013 edition of the Washington Post. Read Article


Demolition of Wing 2 Outer Shell

All of the interior demolition work is done on Wing 2 of the building. Demolition of the outside shell has begun, and is anticipated to be complete by mid to late February 2013.


Demolition of Wing 1 Outer Shell- Completed 15 Jan 2013

All associated demolition work on Wing 1 was completed ahead of schedule on January 15, 2013.


Parking Parcel Work Well Underway

The primary parking surfaces of the parking parcel on Columbia Pike were removed. Removal of the man-made improvements from land formerly occupied by the parking parcel and gas station is progressing well.


Demolition of Wing 1 Outer Shell

All of the interior demolition work is done. Actual demolition of the outside shell has begun, commencing with Wing 1, and is anticipated to be complete by late January to early February 2013.


First Visible Signs of Ongoing Demolition Work

A fence has been erected around the primary parking parcel on Columbia Pike and the former gas station area. Work has begun on the removal of the parking surfaces in the Navy Annex parking lot by milling the pavement in preparation for removal of all of the man-made improvements from the land.


Meeting Held to Address Community Questions and Concerns

On November 15, 2012, Washington Headquarters Services (WHS), along with all stakeholders and partners, held a Navy Annex Demolition Community Meeting to provide further details of the project plan and address any concerns expressed by residents of the Foxcroft Heights community. WHS remains committed to providing the latest information to the community throughout the project's duration to minimize inconveniences to residents.


Navy Annex Demolition Contract Awarded

Throughout the project's duration, relevant information and updates will be posted to the Navy Annex Land Transfer website, to include a demolition schedule. In addition, ongoing outreach efforts will address questions and concerns from members of the community.