Demolition of the Navy Annex
This page is your source for the latest information about the Navy Annex demolition project, led by Washington Headquarters Services. Please Contact Us directly for specific questions or requests regarding this effort.
April 26, 2013
The team uses a variety of construction vehicles and equipment to clear debris after bringing down each wing.
March 21, 2013
The team completed all associated work on Wing 3 of the structure ahead of schedule on March 13.
February 21, 2013
The team completed all associated demolition work on Wing 2 of the structure ahead of schedule on February 8.
January 18, 2013
The Corinthian Contractors Inc. and Demolition Services Inc. (DSI) Joint Venture construction team completed all associated demolition work on Wing 1 of the structure ahead of schedule on January 15.
December 20, 2012
Visible signs of the demolition increased in December 2012 as construction crew members worked from the inside out to begin removing each Wing of the structure.