The Navy Annex demolition project has officially begun with members of Corinthian Contractors Inc. and DSI now on site. Demolition of the building wings is scheduled to begin in November 2012. The initial schedule of key events and milestones is posted below. Washington Headquarters Services (WHS) will post updates to the schedule as they are released in an effort to keep members of the community informed.

The 42 acres currently occupied by the Navy Annex (also known as FOB2), the Navy Exchange Service Station, and associated parking lots are to be demolished with all improvements removed from the property and transferred to the Secretary of the Army. The land will be restored to open green space for use by Arlington National Cemetery. An initial environmental assessment found no significant direct, indirect, or cumulative effects on the quality of the natural or human environment as a result of this project.

WHS, along with project partners, will hold a community Town Hall Meeting prior to the demolition to provide further details of the plan and address any concerns expressed by residents of the Foxcroft Heights community. WHS is committed to providing the latest information to the community throughout the duration of the project to minimize inconveniences to residents.

If you have any questions, please contact WHS at information@whs.mil.

Key Milestones

  • August 27, 2012 - The contract for the demolition of the Navy Annex was awarded to Corinthian Contractors, Inc. and DSI
  • October 2, 2012 - Corinthian Contractors Inc. and DSI took control of the Navy Annex property from the Government in order to begin the demolition process
  • October 2012 - Assessment of facility
  • October 2012 - Abatement of hazardous material begins in Wing 1
  • November 15, 2012 - Community Town Hall
  • November - December 2012 - Demolition of Wing 1 commences
  • November - December 2012 - Abatement of hazardous material begins in Wing 2
  • December 2012 - June 2013 - Demolition of the rest of wings continue following this pattern: Abatement of hazardous material then Demolition commences
  • January 2013 - Parking lots removal process starts
  • March - August 2013 - Grading of Navy Annex site and former parking lots
  • April - August 2013 - Hydro seeding & final grading of site
  • August 2013 - Arlington National Cemetery inspection and acceptance
  • August 2013 - Site turned back to Washington Headquarters Services
  • September 2013 - Official Transfer from Department of Army to Arlington National Cemetery

** Disclaimer: This schedule is subject to change based on the dynamic nature of the demolition process. It will be updated on this site as needed throughout the demolition process.